Pre-Disaster Recovery Plan: Template & Development Guide

June 27, 2023

The included template serves as a customizable document that assists Centralina jurisdictions in developing a pre-disaster recovery plan to address regional resilience and support community and business economic recovery from future disaster events and economic shocks. 

This document helps jurisdictions customize the Pre-Disaster Recovery Plan Template. The Guide serves as a “how-to” manual that accompanies the Template.

Federal funds are commonly passed through state agencies in North Carolina before being awarded to local governments, which can make the original funding source less obvious. Before proceeding with a procurement, local governments should verify whether an award originates from a federal source. This determination affects compliance obligations, including procurement standards, reporting, and audit requirements.

When a construction or repair contract over $300,000 involves a building, the procurement and contract are subject to additional requirements under N.C.G.S. 143-128. Therefore, this question must be answered to determine whether the additional statutory requirements apply to this procurement scenario.

The micro-purchase threshold is a federal procurement threshold under which competitive procurement is not required. The default micro-purchase threshold is $15,000, but local governments may increase the micro-purchase threshold up to $50,000. An explanation of increasing the micro-purchase threshold and a template for the required annual self-certification is available here.